Limpet Dam Installation for Harbour Gate
Maintenance, County Durham

Client

The Seaham Harbour Dock Company

Duration

Approximately 10 days

Location

Seaham Harbour

Share

Seaham Harbour required specialist temporary water control to facilitate essential inspection and maintenance works on the harbour gates.

Working within a live operational harbour, the project involved accessing the gate pintels and roller boxes whilst coordinating multiple contractors, diving operations, lifting activities and confined space working.

A key challenge was the existing harbour structure itself. Formed from ashlar stone, with only historical drawings available, the condition and profile of the invert and connection points were largely unknown. This required a temporary isolation system capable